Project: Tritonis Additional Info

Additional Infomation for Project: Tritonis is provided here


Project: Tritonis full specification

Please see the Project:Tritonis system page here.


Project: Tritonis Timeline

Phases:

  • Research: December 1st - February 5th

  • Design: January 20th - February 5th

  • Purchasing: February 2nd - February 6th

  • Logistics: Feb 3rd - Feb 21st*

  • Building: Feb 21st* - Feb 27th*

  • Testing: Feb 25th* - March 4th*

(*) Tentative dates

Gannt Chart:

Length of time previous systems have been Primary System

  • Imperium: August 1996 - 1 year 10 months

  • Magnus: June 1998 - 8 months

  • Orion: February 1999 - 1 year 6 months

  • Prometheus: August 2000 - 1 year 7 months

  • Hyperion: March 2002 - 2 years 8 months

  • Bellerophon: November 2004 - 2 years 9 months

  • Maxximus: August 2007 - 4 years 5 months

  • Apophis: January 2012 - 3 years 5 months

  • Sicarius: September 2015 - 6 years 5 months

Project Tritonis Purchasing and Logistics Spreadsheet

Project Tritonus