Phases:
Research: December 1st - February 5th
Design: January 20th - February 5th
Purchasing: February 2nd - February 6th
Logistics: Feb 3rd - Feb 21st*
Building: Feb 21st* - Feb 27th*
Testing: Feb 25th* - March 4th*
(*) Tentative dates
Gannt Chart:
Imperium: August 1996 - 1 year 10 months
Magnus: June 1998 - 8 months
Orion: February 1999 - 1 year 6 months
Prometheus: August 2000 - 1 year 7 months
Hyperion: March 2002 - 2 years 8 months
Bellerophon: November 2004 - 2 years 9 months
Maxximus: August 2007 - 4 years 5 months
Apophis: January 2012 - 3 years 5 months
Sicarius: September 2015 - 6 years 5 months